You could copy the code from the repository and host your own, modifying the timezone to your own. I walked through the steps on how to do this using Grist’s Invoice custom widget in our recent Creating Custom Invoices webinar. The steps would be the same, just downloading the files from the correct folder here: GitHub - rague/ws-timeline: Timeline plugin for Grist
Hi Raphael! The timezone now works! It automatically detects I am in London, and the editing is fine. It would still be great to be able to specify the time zone for the control. For example, if I am travelling to New York, it would show everything in New York time (I assume), which would not be good…
Separately, I am trying to filter the data within timeline by conditioning data selection on the other row selected in a different widget, on the top left: BRANCH), but it doesn’t seem to work at all. The link filter state is null. However, if I apply the same logic to other other widget, it does show the filtered data (on another page). I am not sure if the problem is with the timeline, or with the way I set up the link filter. But I am doing it exactly the same as on the other page, and it does filter there, but not on this page where I use timeline… Any ideas?
It seems to be a limitation of the way the link between views works. I’ve started a new thread on the subject here: setSelectedRows and cylic linking
I can’t think of a solution at the moment…
Avez-vous essayé Alt + Molette ou Alt + 2 doigts (trackpad) - dans la colonne de gauche ?
Dans tous les cas, n’hésitez pas à consulter l’aide pour tous les raccourcis (? en haut à gauche)
Hi ! I love your plugin but i’m wondering : could it be possible to adjust the width of the title column ? I’m using rather short group names so the fixed width of their columns takes up a lot a space for nothing :
Et je ne comprends pas pourquoi je récupère le calendrier en anglais alors qu’il s’affiche en français quand je vais directement sur le lien d’exemple.
Désolé, mais ça dépasse mes faibles compétences.
Merci à @Raphael_Guenot pour ce magnifique widget et à celleux qui me répondront pour leur aide.
Your Widget is awesome, it’s going to help us a lot in my hospital.
I’m mainly interested in the Gantt view.
I’ve a small request : I don’t care about the time, only about the date. If I change the column type to only date the widget doesn’t work anymore. Would it be possible to make it so that we can choose only a date format (without time)?
Thanks!
Bonjour !
Votre widget est génial, il va beaucoup nous être utile dans notre CHU.
Je suis principalement intéressé par la vue Gantt.
J’ai une petite demande : l’heure ne m’intéresse pas, seule la date compte. Si je modifie le type de colonne pour n’afficher que la date, le widget ne fonctionne plus. Serait-il possible de faire en sorte que l’on puisse choisir uniquement un format date (sans heure) ?
This is a bit of a silly workaround, but you should be able to have your input columns be Date type and then just have helper formula columns that convert them to DateTime for use in the widget. Example.
You might need to modify the end date to be at the end of the day instead of the default 12am, which I did in the example using DATEADD($Date_Entry_End, days=1).
The thing is, I don’t care about the time at all. So your Example doesn’t help me since the Gantt view is still by hour instead of juste date.
But it’s not the only problem I have with the widget. It’s a good start, but as others have stated, it’s not a real Gantt with dependencies etc. I want to have something of this nature :